Uninstalled materials under ASC 606 and IFRS 15: the zero-margin rule

30 minutes ago
10 min read
Uninstalled materials under ASC 606 and IFRS 15: the zero-margin rule, title over a night city skyline. Data Studios original cover

When a contractor measures progress on a contract with costs incurred, a large piece of third-party equipment delivered to the site before it is installed can distort the percentage of completion overnight. ASC 606 and IFRS 15 deal with this situation through the same converged guidance: when specified conditions are met at contract inception, the cost of the uninstalled good is excluded from the cost-to-cost measure of progress, and revenue for that good is recognized only up to its cost, at a zero margin.


The rule sits in ASC 606-10-55-21(b) and in IFRS 15 paragraph B19(b), and the wording is the same in both. It applies to a good that is not distinct, that the customer controls significantly before the related installation services are performed, whose cost is significant relative to total expected costs, and that the entity buys from a third party without being significantly involved in its design or manufacture. Elevators, generators, switchgear, chillers, packaged HVAC units and specialist medical or production equipment are the typical cases.


The effect on reported results can be large. In the worked example below, a contractor with a $12 million contract and $3.6 million of generators delivered in year one would report $1,350,000 of year-one profit with an unadjusted cost-to-cost method and $720,000 once the uninstalled materials adjustment is applied, a difference of $630,000 that moves into later periods.


··········


WHEN THE UNINSTALLED MATERIALS QUESTION ARISES.


The question only exists for a performance obligation satisfied over time. Both standards require an entity to measure progress toward complete satisfaction of each such obligation, with the objective of depicting its performance in transferring control of the promised goods or services to the customer. A single method is applied to each performance obligation, consistently across similar obligations, and progress is remeasured at the end of each reporting period.


Input methods recognize revenue on the basis of the entity's efforts relative to its total expected efforts, and the most common input in construction and installation contracts is cost incurred. The standards list resources consumed, labor hours, costs incurred, time elapsed and machine hours as examples of inputs. Cost-to-cost works well when costs accumulate roughly in line with the work that transfers to the customer, and it fails when a single cost is incurred early and in bulk without a matching amount of construction or installation effort.


Both standards acknowledge this weakness directly. ASC 606-10-55-21 and IFRS 15 paragraph B19 describe the shortcoming of input methods as the possibility that there is no direct relationship between the entity's inputs and the transfer of control of goods or services to the customer. The entity therefore excludes from an input method the effects of any inputs that do not depict its performance, and for a cost-based method the standards identify two situations in which an adjustment may be required.


The first situation, in ASC 606-10-55-21(a) and IFRS 15 paragraph B19(a), covers costs that do not contribute to progress, such as significant inefficiencies that were not reflected in the contract price, including unexpected amounts of wasted materials or labor. The second situation, in paragraph (b), covers costs that are incurred but are not proportionate to progress, and that second category is where uninstalled materials sit.


··········


THE FOUR CONDITIONS IN ASC 606-10-55-21(B) AND IFRS 15 B19(B).


Under paragraph (b), when a cost incurred is not proportionate to the entity's progress, the best depiction of performance may be to recognize revenue only to the extent of that cost. The standards then describe the case of a good used in satisfying the performance obligation and say that a faithful depiction might be to recognize revenue at an amount equal to the cost of that good if the entity expects, at contract inception, that all of the following conditions will be met.


........


Condition

What the entity assesses

1. Not distinct

The good is part of a single combined performance obligation

2. Early control

The customer obtains control of the good significantly before receiving services related to it

3. Significant cost

The cost of the good is significant relative to total expected costs of the obligation

4. Third-party procurement

The good comes from a third party and the entity is not significantly involved in designing and manufacturing it


........


The fourth condition is read together with the principal versus agent guidance. The entity must still be acting as a principal for the good, which is why the standards cross-refer to that guidance; a contractor that never obtains control of the equipment faces a principal versus agent question instead.


The test is applied with the expectations held at contract inception. A contractor that expects at inception to procure a standard elevator package, take delivery months ahead of installation and pass control to the customer on delivery to the site will meet the conditions; a contractor that designs a bespoke process line and fabricates part of it in its own workshop will generally fail the fourth condition, and the cost of that equipment stays inside the cost-to-cost measure.


The guidance is written in permissive terms ("may be", "might be") because the overriding objective is a faithful depiction of performance. In practice, once all four conditions are met, the zero-margin treatment is the depiction both standards point to, and the FASB's Example 19 on uninstalled materials applies it without alternatives.


··········


HOW THE ZERO-MARGIN ADJUSTMENT WORKS.


The adjustment has two parts that must be applied together. The cost of the uninstalled good is removed from both the numerator and the denominator of the cost-to-cost calculation, and the same amount is removed from the transaction price before the progress percentage is applied. Revenue for the good is then recognized separately, equal to its cost, when the customer obtains control of it.


FASB Example 19 in ASU 2014-09 (ASC 606-10-55-187 to 55-192) shows the mechanics. An entity agrees in November 20X2 to refurbish a three-story building and install new elevators for total consideration of $5 million, with expected costs of $4 million including $1.5 million for the elevators. The elevators are delivered to the site in December 20X2 and installed in June 20X3. At December 31, 20X2, other costs incurred are $500,000 out of $2.5 million, so progress is 20 percent; revenue is $2.2 million (20 percent of $3.5 million plus $1.5 million), cost of goods sold is $2 million and profit is $200,000.


The resulting pattern is a zero margin on the equipment and the full contract margin on the remaining work. In the FASB example the overall contract margin of $1 million is earned entirely on the $2.5 million of other costs, so the margin percentage on the installation and refurbishment work is higher than the blended contract margin. Finance teams that track project margins against the blended estimate need to expect this.


··········


WORKED EXAMPLE: GENERATORS IN A DATA CENTER CONTRACT.


The following figures are illustrative. A US contractor signs a fixed-price contract in 2026 to build out a data center hall, including the supply and installation of backup generators, for $12,000,000. The work is a single performance obligation satisfied over time, and progress is measured with costs incurred. The generators are purchased from a manufacturer for $3,600,000, are delivered to the customer's site in 2026, and control passes to the customer on delivery; installation and commissioning take place in 2027 and 2028. The contractor does not design or manufacture the generators and acts as a principal.


........


Item

Amount ($)

Transaction price

12,000,000

Generators (third-party cost)

3,600,000

Other expected costs

6,000,000

Total expected costs

9,600,000

Expected contract profit

2,400,000

Transaction price excluding generators

8,400,000


........


All four conditions are met at inception: the generators are not distinct from the build-out, the customer controls them well before installation, their cost is 37.5 percent of total expected costs, and the contractor buys them from a third party. Other costs incurred to date are $1,800,000 at December 31, 2026, $4,500,000 at December 31, 2027 and $6,000,000 at completion in 2028.


........


Year

Progress on other costs

Cumulative revenue ($)

Revenue in year ($)

Cost in year ($)

Profit in year ($)

2026

30%

6,120,000

6,120,000

5,400,000

720,000

2027

75%

9,900,000

3,780,000

2,700,000

1,080,000

2028

100%

12,000,000

2,100,000

1,500,000

600,000

Total



12,000,000

9,600,000

2,400,000


........


The 2026 revenue is 30 percent of $8,400,000, which is $2,520,000, plus $3,600,000 for the generators at cost. Without the adjustment, costs incurred of $5,400,000 divided by $9,600,000 would give 56.25 percent progress and revenue of $6,750,000, producing a year-one profit of $1,350,000 instead of $720,000. The $630,000 difference is margin on installation work that has not yet been performed.


Assume the contractor bills $5,000,000 in 2026 and collects $4,000,000 of it. The 2026 entries are set out below.


........


Entry

Account

Debit ($)

Credit ($)

1. Generators received

Inventory: contract materials

3,600,000


1. Generators received

Accounts payable


3,600,000

2. Control passes on delivery to site

Cost of revenue: generators

3,600,000


2. Control passes on delivery to site

Inventory: contract materials


3,600,000

3. Other contract costs

Cost of revenue: other contract costs

1,800,000


3. Other contract costs

Cash, payables and accrued payroll


1,800,000

4. Revenue for the year

Contract asset

6,120,000


4. Revenue for the year

Revenue


6,120,000

5. Billing

Accounts receivable

5,000,000


5. Billing

Contract asset


5,000,000

6. Collection

Cash

4,000,000


6. Collection

Accounts receivable


4,000,000

Total


24,120,000

24,120,000


........


At December 31, 2026 the contractor reports a contract asset of $1,120,000 (revenue of $6,120,000 less billings of $5,000,000) and accounts receivable of $1,000,000. The split between contract assets and receivables follows the usual rules explained in the site's comparison of contract assets vs contract liabilities under IFRS 15 and ASC 606.


··········


UNINSTALLED MATERIALS: IFRS 15 VS ASC 606 COMPARISON.


The requirements on measuring progress and uninstalled materials were issued jointly and are worded identically. The differences that surround them come from the wider frameworks in which each standard sits.


........


Topic

ASC 606 (US GAAP)

IFRS 15

Uninstalled materials guidance

ASC 606-10-55-21(b)

Paragraph B19(b)

Four conditions

Same

Same

Illustrative example

Example 19, ASC 606-10-55-187 to 55-192

Illustrative Example 19

Change in progress estimate

Change in estimate under Subtopic 250-10

Change in estimate under IAS 8

Expected loss on the contract

Loss provision under ASC 605-35 for construction-type contracts

Onerous contract provision under IAS 37

Contract costs

ASC 340-40

IFRS 15 contract cost guidance


........


The loss contract row needs attention. Excluding the generators from the progress measure does not change the total expected contract result, and if total expected costs exceed the transaction price, US GAAP still requires a provision for the anticipated loss on construction-type contracts while IFRS applies the onerous contract test in IAS 37. The two approaches can produce different amounts, as set out in the site's analysis of onerous contracts under IAS 37 vs US GAAP loss contract provisions.


··········


PRESENTATION AND DISCLOSURE OF COST-TO-COST REVENUE.


Revenue recognized on the uninstalled good is presented as revenue from contracts with customers in the same line as the rest of the contract, and the cost of the good is presented in cost of revenue in the period control transfers. The zero-margin amount does not create a separate performance obligation and is not disclosed as one.


Both standards require entities to disclose the methods used to recognize revenue for performance obligations satisfied over time and why those methods faithfully depict the transfer of goods or services, together with the significant judgments made in applying the standard. A contractor that applies the uninstalled materials adjustment on a material scale should describe it in the accounting policy for measuring progress, because it changes the timing of margin recognition across periods.


Contract balances are also affected. Recognizing revenue for equipment at cost on delivery often increases the contract asset if billing milestones lag delivery, or reduces a contract liability if the customer paid an advance for the equipment. The contract balance roll-forward and the explanation of significant changes in contract assets and liabilities should reflect large equipment deliveries in the period.


··········


COMMON ERRORS WITH UNINSTALLED MATERIALS.


The most frequent error is applying the adjustment to materials whose control has not yet passed to the customer. Equipment sitting in the contractor's own warehouse is inventory, and its cost is excluded from the progress measure under the general requirement to exclude goods or services for which control has not transferred (ASC 606-10-25-34 and IFRS 15 paragraph 42). Revenue at cost is recognized only when the customer obtains control, which in many contracts is delivery to the customer's site.


A second error is removing the cost of the good from the cost-to-cost calculation while leaving the full transaction price in place. That produces a progress percentage on other costs applied to the whole $12,000,000, which overstates revenue. The adjustment works only when the cost is removed from the measure and the same amount is removed from the transaction price.


A third error is treating every large purchase as uninstalled materials. Steel, concrete and cabling consumed continuously during construction are inputs that track performance, and customized equipment the contractor designs or partly fabricates fails the fourth condition. The cost of those items stays in the measure of progress.


The fourth error concerns subsequent changes. The conditions are assessed at contract inception, but estimates of total costs and the equipment cost itself can change. A change in the expected cost of the generators or of other costs is a change in estimate, recognized on a cumulative catch-up basis through the progress measure, under Subtopic 250-10 for US GAAP and IAS 8 for IFRS. Costs of significant inefficiencies, such as equipment damaged and replaced at the contractor's expense, fall under paragraph (a) and are excluded from the measure because they do not contribute to progress; the related costs are expensed as incurred.


··········


PRACTICAL CHECKLIST FOR CONTROLLERS.


1. Identify over-time contracts measured with costs incurred that include significant third-party equipment.


2. Document the inception assessment of the four conditions for each item, including the cost as a percentage of total expected costs and the expected gap between control transfer and installation.


3. Confirm the control transfer point for the equipment in the contract terms, such as delivery to the customer's site.


4. Remove the equipment cost from both the cost-to-cost numerator and denominator, and remove the same amount from the transaction price.


5. Recognize revenue equal to the equipment cost when control transfers, and apply the progress percentage on other costs to the reduced transaction price.


6. Reconcile project margin reports so that the zero margin on equipment and the higher margin on other work are visible to project managers.


7. Test the total contract for an expected loss under ASC 605-35 or IAS 37 independently of the progress calculation.


8. Update the accounting policy and the significant judgments disclosure when the adjustment is material.


··········


ZERO-MARGIN REVENUE ON UNINSTALLED MATERIALS: JUDGEMENT AREAS.


The mechanics are identical under ASC 606 and IFRS 15: when the four conditions are met at inception, the cost of the uninstalled good is taken out of the cost-to-cost measure and out of the transaction price, and revenue equal to that cost is recognized when the customer obtains control. The contract's total profit is unchanged, and the adjustment only moves margin from the period of delivery to the periods in which installation work is performed.


The judgement sits in the conditions. Whether a cost is "significant" relative to total expected costs has no bright line in either standard, whether control passes "significantly before" installation depends on the contract timeline, and whether the contractor is "significantly involved" in design or manufacture depends on the actual engineering work it performs. Entities should set a documented policy for these thresholds, apply it consistently across similar contracts, and keep in mind the separate loss provision rules, which still differ between US GAAP and IFRS. The site's article on construction contracts using the percentage-of-completion method covers the wider cost-to-cost mechanics on which this adjustment is built.


··········